Scandal fallout plagues Duke Energy’s Edwardsport project
Regulatory proceedings involving the coal gasification plant are being delayed while investigations continue over conflicts of interest at the IURC.
Regulatory proceedings involving the coal gasification plant are being delayed while investigations continue over conflicts of interest at the IURC.
The commission is summoning the CEO of North Carolina-based Duke Energy to justify the $2.9 billion Edwardsport plant on the same day the state ethics board filed formal charges against a former IURC attorney hired by Duke.
The renovations complied with Indiana’s plan for implementing the federal Clean Air Act, a three-judge panel of the U.S. Court of Appeals in Chicago said in Tuesday’s ruling.
Decision to replace Indiana CEO Mike Reed, who has been placed on administrative leave, follows a state investigation into an ethics controversy involving Duke that resulted in the dismissal of the chairman of the Indiana Utility Regulatory Commission.
The Indiana Utility Regulatory Commission canceled a hearing set for Thursday on Duke Energy Corp.’s controversial Edwardsport power plant amid a conflict-of-interest scandal that cost the agency’s chief his job.
Duke Energy Corp. placed Mike Reed, CEO of its Indiana operations, on administrative leave Tuesday afternoon amid a state investigation that involves the company and resulted in the dismissal of the chairman of the Indiana Utility Regulatory Commission.
Daniels administration alleges Indiana Utility Regulatory Commission chairman David Lott Hardy knew an administrative law judge was talking with Duke Energy Corp. about a job even as he presided over a Duke case.
Consultant finds 23 or so customer-service jobs may be unneeded after Citizens Energy acquires city water and sewer utilities. Administrative jobs may also be on bubble, though most savings are from capital-related expenses.
Joseph Biggio, who was executive vice president of operations at Ecological Systems Inc. from 2001 through 2007, was charged Thursday with two counts of violating the Clean Water Act and one count of making false statements.
A proposed settlement between the utility and industrial customers would temporarily cap the cost of the plant, which is $1 billion more than initial estimates.
Farming groups have urged the U.S. Environmental Protection Agency to retain its current standards for dust, soot and other microscopic particles, arguing that tighter restrictions would be unworkable.
The draft net metering rule would boost the state’s power cap for renewable power units and expand it to all customer classes served by electric utilities.
The Indiana Department of Environmental Management’s top attorney asked agency staff to change how they cite companies for
violating the state’s water pollution law.
Indiana Utility Consumer Counselor David Stippler’s comments came four months after Duke Energy revealed the cost of its southwestern
Indiana plant had grown to nearly $2.9 billion, or about twice the project’s original 2007 estimate.
Rural electric cooperative to pay civil penalty of nearly $1 million for not using most modern pollution controls. Hoosier Energy also to spend up to $300 million on pollution controls at coal-fired plants.
Sale of city's water and sewer utilities faces showdown on Monday with full council vote.
The Indiana Department of Environmental Management says the rule would impact sewage treatment plants upstream of lakes.
Indiana’s utilities are scrambling to assess the cost of tighter air pollution limits proposed this month by the Environmental Protection Agency that could drive up electric rates.
Transmission lines costing about $16 billion are needed to move wind energy into the electric grid. But the cost has sparked
a debate over who should pay for getting the power from where it is made to where it is consumed.
Ohio’s governor has asked state environmental regulators to come up with a way to save 214 jobs at a northwest Ohio plant
that is considering a move to Indiana.